| An AI-generated rendering of the Temelín nuclear power plant. |
South Korea and France are stepping up preparations to compete for contracts to build Units 3 and 4 of the Temelín nuclear power plant in the Czech Republic, ahead of a construction decision expected next year. While the South Korean government has formally expressed its intention to secure additional orders and Korea Hydro & Nuclear Power (KHNP) is expanding its local supply chain, France's EDF, which lost the tender for the Dukovany nuclear power project, continues to engage with the Czech government and industry. Negotiations over a potential equity investment in U.S.-based Westinghouse and European Union (EU) industrial regulations have further complicated South Korea's efforts to maintain its competitive advantage.
According to the Ministry of Trade, Industry and Resources (MOTIR) and other sources on Oct. 25, Minister Kim Jung-kwan held a video conference with Czech Minister of Industry and Trade Karel Havlíček on Oct. 20, requesting further cooperation on Temelín Units 3 and 4. Kim also sought diplomatic support from the Czech government, expressing concern that the European Union's proposed Industrial Accelerator Act could restrict South Korea's participation in the European nuclear power market.
The Czech Republic is expected to decide in 2027 whether to proceed with the construction of two new reactors at Temelín. In January, Havlíček said that despite South Korea's existing preferential negotiation option, the Czech government would "give French and American companies an opportunity to submit price proposals and compare the terms offered by other bidders." Czech energy company ČEZ also described KHNP's option as "non-binding" in its investment prospectus. This means that winning the Dukovany contract does not guarantee KHNP a contract for Temelín.
France's EDF, which lost the Dukovany tender, has continued its engagement with the Czech government and industry. Following a meeting with French companies attended by the Czech industry minister in March, EDF also participated in an industrial cooperation event in Brno on Oct. 7 attended by industry ministers from both countries. During the Dukovany bidding process, EDF competed against South Korea by emphasizing greater participation by Czech companies. After losing the tender, it filed a lawsuit challenging the outcome, temporarily halting KHNP's contract signing.
A potential equity investment has emerged as a new factor in South Korea's relationship with Westinghouse. Plans for South Korea to acquire a 5–10% stake in the U.S. company were formally announced last month, raising the possibility of closer cooperation between the two sides. However, it remains uncertain whether this would eliminate their potential rivalry over Temelín. Westinghouse is participating in the new Dukovany project as a subcontractor to KHNP, but it is also among the U.S. companies mentioned by the Czech government as possible bidders for the Temelín project.
KHNP is also preparing for a potential Temelín contract by leveraging the workforce and supply chain it has established for the Dukovany project. In a recent interview with Czech media, KHNP's local construction manager said, "If we participate in the Temelín project, we will be able to draw on the licensing specialists and construction capabilities that have gained experience at Dukovany." The official added, "Having the same contractor build subsequent nuclear reactors would generate cost savings through economies of scale, reduce project risks and shorten construction periods."
KHNP is also expanding supply chain cooperation with Czech companies in preparation for a potential Temelín order. At an event on Oct. 14 attended by 17 South Korean companies and approximately 50 Czech companies, KHNP signed 34 memorandums of understanding. For the Dukovany project, however, the company is considering adjusting procurement schedules for certain equipment to account for the time Czech suppliers need to obtain American Society of Mechanical Engineers (ASME) certification.
ČEZ has said that KHNP's option to supply two new reactors at Temelín is subject to a limited price validity period. If the Czech government also considers proposals from American and French companies, the outcome of South Korea's bid is likely to depend heavily on the final price competition.
"To ensure that nuclear power plant construction plans within the EU proceed without disruption, cooperation with countries that have strong supply chains, such as South Korea, is essential," Kim told the Czech side. He also urged the Czech government to "continue its diplomatic efforts within the EU to ensure that the proposed Industrial Accelerator Act does not hinder cooperation between our two countries."
Jeong Soon-young